Stockton, California
Client:
- Steve Keeter
San Joaquin County Capital Projects Division
100 W. Mathews Road, French Camp, CA 95231
Chronology:
- Start Design – May 1999
- Phase One Complete Design – Spring 2001
- Phase One Start Construction – Summer 2001
- Phase One Complete Construction – December 2001
- Phase Two Complete Design – September 2001
- Phase Two Start Construction – January 2002
- Phase Two Complete Construction – October 2003
Construction Value:
- Phase One – $1,124,500
- Phase Two – $13,717,729
Designers:
- Kaplan McLaughlin & Diaz (Programming thru DD), San Francisco Office
- J.R. Romero, AIA (CDs thru CA – while employed by another firm)
Major Consultants:
- Civil Engineer – Kjeldsen Sinnock & Neudeck, Stockton, CA
- Structural Engineer – Ingraham – DeJesse & Associates, Berkeley, CA
- Mechanical/Plumbing Engineer – Ainsworth & Associates, Sacramento, CA
- Electric Engineer – MSA Engineering, Inc., Reno, NV 89509
- Landscape Architect – Schoenberg & Associates, Reno, NV
Phase One Contractor: AM Stephens Construction Company, Inc., Lodi, CA
Phase Two Contractor: Howard S. Wright Construction, Sacramento, CA 95825

San Joaquin County Mental Health Facility - Family Health Building (rear view)

San Joaquin County Mental Health Facility - Family Health Building (front view)

San Joaquin County Mental Health Facility - Adult Services Building and purseforum prada wallet purseforum prada wallet purseforum prada wallet Courtyard

San Joaquin County Mental Health Facility - Adult Services Building Lobby
(Photos by Gypsy Dog Imagery)